As per current NATSPEC except as follows:
Report
A site investigation was made and a copy of the entire report is included in the Appendix for reference.
As per current NATSPEC.
As per current NATSPEC except as follows:
As found site conditions
GUIDE NOTE: Delete subclause “Topsoil Stockpiles” nominated in NATSPEC, Building Template/Worksection and include the following:
Topsoil stockpiles
Stockpile site topsoil approved for re-use, and imported topsoil before placing as specified in SG / LANDSCAPE SOILS. Establish stockpiles in directed locations, to heights not exceeding 1.5m. Provide drainage, erosion protection and aeration. Do not remove plant growth occurring during storage unless approved. Do not allow traffic on stockpiles. If to remain for more than four weeks, sow with approved temporary grass
General
Loose fill: Maximum loose layer thickness of 150mm.
Moisture content
Consult structural/civil engineer for the % moisture content requirements.
Settlement of earthworks
Fill, compact and trim all settlements of earthworks which take place during construction. Dig out soft spots or unsound areas and fill with sound material properly compacted to a condition equivalent to the surrounding material.