The drainage systems within school facilities includes all the associated pipework and services for the removal and disposal of sanitary drainage and stormwater management in two separated systems. This section covers the Stormwater drainage system.
Refer to DG / DRAINAGE (& TRADE WASTE)
The stormwater drainage services is to be designed from a “Whole of Life” (WOL) perspective to provide:
Refer to NATSPEC 0821 Stormwater - Buildings for Australian Standards and relevant cross sections
Refer to NATSPEC 0821 Stormwater – Buildings for acoustic treatment of piping.
Design the stormwater system to allow for known future stages of the development of the site, including the use of demountable buildings.
Refer to NATSPEC 0821 Stormwater – Buildings for Stormwater detention tanks & pumps requirements
Refer to DG/ WATER Section for rainwater reuse considerations.
GUIDE NOTE: Existing Stormwater to be investigated and assessed by the project’s civil & hydraulic engineers prior to commencing work.
GUIDE NOTE: Refer to NATSPEC 0821 Stormwater – Buildings for trenching, bedding & surrounds requirements.
Provide:
GUIDE NOTE: Refer to NATSPEC 0882 Hydraulic Electrical Minor for all Electrical Installations requirements.
GUIDE NOTE: Provide dilapidation report prior to the commencement of work.
The Water Cycle Management Study is to include the following considerations:
GUIDE NOTE: Refer to NATSPEC 0821 Stormwater – Buildings for testing, commissioning & as built requirements. Documentation must comprise final construction drawings to be used in conjunction
with the technical specification in current NATSPEC format.
Include the following on drawings: