
Published: 2021-03-11 16:05:33 - Exported: 2024-09-04 16:34:29 | NB | The information on this sheet once printed/exported is classed as an uncontrolled copy. The currency of the information should be checked by visiting the ESFG website prior to using the information for any purposes.
Published: 2021-03-11 16:05:33 - Exported: 2024-09-04 16:34:29 | NB | The information on this sheet once printed/exported is classed as an uncontrolled copy. The currency of the information should be checked by visiting the ESFG website prior to using the information for any purposes.
Provide at least the following electrical services in Schools:
Provide the additional electrical services in schools where required:
The completed system is to meet the regulatory requirements of the following:
As part of the Design process the following documentation is to be produced, for all jobs:
Provide construction and work-as-executed drawings in industry recognised DWG CADD file format as well as PDF format.
All drawing sets are to include:
Ensure that permanent electrical supply can be made available.
Engage an Accredited Service Provider Designer (ASP/Level3) to prepare the Application for Connection of Load for the local electricity Distribution Network Service Provider (DNSP) as soon as practicable.
To determine the availability of supply the Accredited Service Provider Designer will require information on what is proposed, including:
The following information will also be required:
Substation Location
The preferred location for the substation is at the site boundary to the road reserve (away from school play ground). There may be situations where this may not be the most cost effective solution:
Alternate substation locations need to be discussed with DoE to ensure that they are appropriate and do not pose a risk to the school community. Generally, locate substations adjacent to the school car park as this allows access for maintenance and locates the substation away from play areas. 24 hour access to the substation will be required, any gates must allow dual key access.
With deregulation of the electricity industry provision of electricity supply is divided into two categories:
Monopoly work is to commence as soon as possible in the design phase. The electrical project officer submits forms on behalf of DoE (as the developer) to the DNSP along with payment of any fees.
Contestable work (both design and construction):
A Level 3 Accredited Network Service Provider should be engaged as part of the design process and the design documents should be included with the tender documents.
Construction work should be included as part of the contract works. Construction work should be based on advice as received from the DNSP. The Contractor is to provide the contestable services using an Accredited Network Service Provider:
A Level 1 ASP will be required to extend the overhead or underground network to reach the school property, or if the capacity of the existing network needs to be increased. This may include high and low voltage works, substations and metering.
A Level 2 ASP will be required to:
If a sub-station and/or HV cable easement is required, notify the client in writing so that Forms from the DSNP may be signed agreeing to provide an easement.
Where a site is to be serviced from a street pole adjacent to the boundary, request permission to utilise the electricity distributor’s distribution pole. This is preferable to installing an additional consumer’s pole on the school property. Use a pillar box with protective device at the property boundary as the point of supply.
A quick connection point for emergency backup portable generators is required for all projects in new and refurbished schools that are identified as at risk of power loss due to bushfire, flood, adverse weather events, and schools identified as a Community Evacuation Facility (CEF).
The MSB design shall provide a quick connection point in the form of a Power Lock or Busbar Cable connection facility to a temporary mobile generator which may be installed in the event of a prolonged power supply failure. The connection facility and generator capacity shall provide for full operation of the school.
Location of temporary portable generator
The portable generator may be positioned up to 200m maximum from the MSB without voltage drop.
Truck Access
Design is to allow for vehicle access to the MSB (including trucks for delivery of the generator and refuelling), space provision for the portable generator and potential noise impacts to learning spaces and adjacent properties caused by operation.
Delivery: Access for large trucks, refuelling tanker and crane is required. A generator is delivered to site on a trailer. It can be left on the parked trailer, or lifted off the trailer with a side loader and placed on the ground, or lifted off the trailer by a mobile crane and placed closer to the MSB. A typical containerised 500kVA portable generator is 6m long x 2.4m wide x 2.6 high, Weight with fuel 10800kg, 1289 litre fuel tank capacity.
Generator: The Generator will need to be installed in a level location cleared of vegetation and any other obstruction to the operation of the generator and ideally no overhanging foliage. In some instances there may be a requirement to house a more permanent generator for a longer period. In this instance, provision must be made for servicing of the generator to ensure its ongoing operation. Location of the generator should not impact universal access to the site. Any connection cables from the generator to the MSB must be suitably secured to not provide a trip hazard.
Refuelling: Typically the generator supplier refuels the inbuilt tank on the generator. Fuel consumption and generator use is monitored remotely. A diesel tanker requires access to refill the generator when needed. If operating at max capacity 8 hrs/day – the generator will typically require to be refilled every 2nd day. In preparation for refuelling, sandbags should be installed as a barrier around the generator to ensure that any diesel spills during refuelling are contained.
Vehicle Safety: Allow for safe manoeuvring and parking of the diesel fuel tanker, with no safety risk to students and adult users of the school or the public is required in assessing location of the generator. Provide bollards where truck access is adjacent to buildings or student play and circulation areas.
Acoustic impact on school operation
Noise generated by the portable generator has potential impact on school teaching operations and adjacent residential areas. An Acoustic Report evaluation of acoustic impact on learning spaces, library, admin and staff is to be considered in assessing the location of the generator.
With Deregulation of the electricity industry, electricity for any site may be purchased on a competitive basis from a NSW licensed electricity retailer. The retailer may be different to the local Distribution Network Service Provider.
All schools are eligible to purchase electricity using the NSW Procurement Electricity Contracts 777& 776.
NSW Procurement Electricity Contracts are to be used. Rates and assistance are available from NSW Procurement.
The school site is to use or remain on the government electricity contract.
Note 1: All DoE sites using an electricity contract are to purchase a minimum percentage of Green Power, currently 6% (2014).
The system is to include an electricity meter type as per the National Electricity Rules and DNSP requirements.
NSW Procurement has a meter contract where DNSP provides metering for Comms 4D Meters if standard meters or Comms 4C if CT Meters.
Only the incumbent retailer can request a metering change so this should be coming through the electricity retailer as part of the new connection/contract process.
All new schools and projects are to include a data cable outlet and power outlet installed near electricity meter. It should also include a telephone line for metering communication. The meter is panel-mounted and requires provision for voltage and current connection, either directly or via current transformers as for standard metering
A tariff analysis and electricity contract decision for a new building/site must be made prior to project practical completion.
When all options have been investigated and a tariff decision cannot be made, the Project Manager is to advise DoE of the outcome so that a follow up analysis can be scheduled within two months.
For guidance:
The procedure is:
Ensure effective coordination between disciplines.
Organise the information from all sources to meet a set program.
The design of the electricity supply system and the selection of equipment is to be undertaken based on a Whole of Life approach to ensure that the completed system provides:
During the design process, and by the Developed Design stage:
Contact the local Telstra District office regarding specific requirements especially earthing details for communications system.
Locate the site MSB optimally with due regard to:-
Final main switchboard location will be influenced by discussions with Architects and the respective electricity distributor.
Provide an engraved notice near the main public entry door to the administration block indicating the location of the main switchboard.
House the MSB in a separate main switchroom with the following features:
Refer to DG / ELECTRICAL SERVICES / CABLE DRAW-IN PITS
A typical drawing detailing the pit dimensions and architectural, structural & hydraulics requirements of the pit is included in the Specification Guide
Refer to DG DRAWINGS / MAIN SWITCHBOARD CUPBOARD PIT
Generally comply with secondary school switchroom requirements.
Refer DG / ELECTRICAL SERVICES / ROOMS AND CUPBOARDS FOR MSB / SECONDARY SCHOOLS
There may be situations where only a cupboard may be required for the main switchboard rather than a switchroom. Provide a cupboard with the following features:
If meters are located in a separate cupboard adjacent to the MSB cupboard, the meter cupboard size should be a minimum 1.2m x 1.2m x 0.6m deep, subject to approval by the local electricity Distribution Network Service Provider. Provide a pair of cupboard doors the same size as the cupboard.
If the meter and MSB are located in the same cupboard, the minimum clear internal dimensions are to be either (2.6W x 0.7D x 2.5H) or (2.0W x 1.5D x 2.5H preferred option).
Electrical Distribution Boards are to be readily accessible, situated within a cupboard specifically designed for the purpose and strategically located to reduce cable runs.
Refer to DG / ELECTRICAL SERVICES / CUPBOARDS FOR ELECTRICAL DISTRIBUTION BOARDS
Allocate EDBs within each building on the following basis:
Refer to DG / ELECTRICAL SERVICES / RETICULATION DESIGN
DG / ELECTRICAL SERVICES / CONDUITS IN CONCRETE
In every new building, and wherever possible in old buildings, provide lockable cupboards for EDBs. Where this is not possible EDBs need a lockable door. Locate cupboards so that access is available only directly from general circulation areas. It is not acceptable to walk through classrooms etc. to gain access to EDBs, or to locate them in storerooms.
These cupboards should have the following features:
Illuminate all EDBs to minimum 160 lux. Install lighting and a double socket outlet within each cupboard or switchroom.
The DNSP will provide details of point of supply and connections to its equipment. For aesthetic and safety considerations, permanent electrical supply is to be reticulated underground.
In all cases, the service/consumers mains must be fire protected, preferably by installation underground or under concrete slabs.
Run service/consumers mains clear of buildings where possible. Consult with the Architect to ensure the planned route does not interfere with future development.
It is quite common for schools to undergo major modification during their life-time, resulting in increases of up to 30% in electrical load. This is usually beyond the capacity of the original service/consumers mains. The original service/consumers are either discarded entirely, or a parallel set is needed.
The table below nominates the minimum service/consumer’s mains capacity to be installed for schools, based on student numbers or school type.
The tables provide a direction on the consumer main size required. The designer should complete a maximum demand calculation for confirmation.
The minimum current capacity must be achieved while also complying with the AS voltage drop requirements for that minimum electrical load.
Where service mains (a direct connection to substation low voltage terminals) are to be installed, the minimum cable size must also comply with the network authorities requirements for fault levels withstand (nominally minimum 240 mm² Cu cable).
Service/Consumers mains to be copper conductor cables. Aluminium conductor cables are not to be used from the Point of Supply.
An acceptable solution, when service/consumers mains need to be larger than 240 mm2, is the following:
In many instances, demountables are installed on site soon after the completion of the permanent accommodation. Ascertain the numbers, locations and types, then design and install the reticulation system to cater for them. Note in particular that demountables use reverse cycle air-conditioning.
In all cases, allow the spare capacities detailed.
Refer to DG / ELECTRICAL SERVICES / SPARE CAPACITY
Note that some DNSP’s require double insulated cables in HD-uPVC conduit. Further, where fire protection equipment and/or lifts are proposed, comply with relevant requirements of AS.
Refer AS3000
Number of enrolled students | Minimum Service/Consumers Mains Capacity | ||||
---|---|---|---|---|---|
|
|||||
1 to 50 | 100 Amps/phase | ||||
51 to 200 | 200 Amps/Phase | ||||
201 or more | 400 Amps/phase |
Number of enrolled students | Minimum Service/Consumers Mains Capacity | ||||
---|---|---|---|---|---|
|
|||||
NA | 400 Amps/phase |
Number of enrolled students | Minimum Service/Consumers Mains Capacity | ||||
---|---|---|---|---|---|
|
|||||
1 to 600 | 500 Amps/phase | ||||
601 to 1,000 | 630 Amps/phase | ||||
1,001 or more | 800 Amps/phase |
Generally, submains may be run underground, or within the building structure (on cable tray, ladder or troughing). During planning, take into account relevant site features and choose routes that will not affect future building development.
Submains are to be copper conductor cables. Aluminium conductor cables are not to be used.
Provide spare capacity as stated.
Refer DG / ELECTRICAL SERVICES / SPARE CAPACITY
Conduit diameters to be sized in accordance with the relevant AS and general installation practices.
The follow space factors are recommended.
0-10 metres 50% space factor for single cables
40% space factor for multiple cables
10-30 metres 33% space factor
30+ metres 25% space factor
Each 90 degree change of direction is to be considered equivalent to 10 metres of conduit run.
Wherever practicable, run other services in the same trench as the electrical cables with due separation of services, both for safety and to avoid interference. This limits excavation costs and avoids a network of underground services, which could interfere with future site development.
Refer to DG / COMMUNICATIONS
Provide as a minimum the following spare conduits with draw cords along all cable routes:
Larger conduits will be required for many runs. Size conduits in proportion to those installed for the initial installation.
From each EDB provide at least the following spare conduits:
Instead of running a number of small diameter conduits, a smaller number of larger diameter conduits (say 50mm) allow greater flexibility of use. Smaller conduits may then be extended as required via an underground junction box or cable pit.
Underground cable draw-in pits should be installed in suitable locations to minimise damage during initial installation or subsequent replacement of cables. However, minimise the use of pits as they are expensive, lead to drainage and insulation problems and are subject to damage.
Provide pits under large switchboards to allow entry of large cables and to facilitate turning these cables to enter the switchboard. Pits are to be drained to the stormwater system via a valve that will prevent surcharging. In addition, the floor of each cupboard or switchroom containing a pit must drain to the outside of the building.
Acceptable pits include:
Any electrical/communications pit should be:
Care must be taken on a sloping site with conduits entering pits, to prevent the ingress of water via the pits and conduits into switchrooms and EDB cupboards. Effectively seal these conduits at both ends.
Consult with the Architect and Hydraulic Engineer to ensure drainage provisions are made and the pit is included in the Architectural documents.
Pits are not to be used to join cables.
Communication services and security services must be supplied with their own separate pits.
Switchboards and equipment must be of current and proven design and in accordance with the requirements of the local DNSP and the relative AS.
Design and manufacture switchboards for the current rating of the incoming mains and fault level that is expected with electricity supply necessary for the completed school.
Refer to DG / ELECTRICAL SERVICES
Provide all indoor switchboards with minimum IP42 rated enclosures with only the operating toggle of control equipment such as circuit breakers protruding through escutcheons or covers. Provide escutcheons or covers with fixings that require a tool be used for their removal.
An overall door with a PWD E-key lock with 2 set of keys is required at any switchboard that is not in a plant room, switchroom or switchboard cupboard.
Single-phase boards are not to be used except in very special cases.
Do not use fuses for overcurrent protection.
Single line diagrams on contract documents for all power distribution and mechanical boards should show:
For an externally located switchboard, eg. in the open space of a demountable school, its enclosure shall be IP 56 minimum. All external Swtichboards must include anti-condensation heaters as per NATSPEC requirements.
Incorporate single line diagrams into contract documents so that all relevant information including notes are received by the switchboard manufacturer during the tender period. This can be achieved by placing the information on sheets separate from site plans, floor plans, etc. Cross-reference the notes to the relevant specification clauses.
Where single line diagrams are placed on drawings with other information, place any relevant notes adjacent to the diagram.
Where the total connected electrical load exceeds 100 amps per phase use one of the following options:
The main control on all MSBs shall be a fault make and load break switch, which will be on the load side of the Service Protection Device (SPD) for MSB local isolation. Generally house the MSB in a switch room, external MSB is not to be installed unless approved by the Electrical Engineer representing DoE.
Refer to DG / ELECTRICAL SERVICES / ROOMS AND CUPBOARDS FOR MSB'S
Include electricity-metering requirements as described elsewhere in the Design Guide and as acceptable to the local electricity DNSP.
Separate metering for the canteen or FSU is required, so provide separate metering within the MSB along with separate submains and an EDB for the canteen or FSU.
Include metering current transformers and potential fuses within the MSB, but the meter/s may be on a separate panel adjacent to the MSB where it is in a switchroom or switchboard cupboard. Consider an option of locating meter panels externally to the MSB Switchroom/Cupboard, complying with the DNSP’s requirements, for both modified and new main switchboards.
Where the rating of consumer’s mains exceeds 100 amps per phase, include a three-phase digital power meter in the MSB along with associated current transformers and potential fuses. Indication is required of:
Provide a machine engraved label adjacent to meter reading:
METER TO BE RESET BY AUTHORISED PERSONNEL ONLY – BEFORE RESETTING ENTER MAXIMUM DEMAND READINGS IN SCHEDULE.
Provide surge protection devices at the Main Switchboard and for communications equipment as recommended by AS1768.
Provide a point of entry 3 phase shunt diverter for the incoming 415 volt supply. The surge protection shall have an indicator showing surges received.
Point of entry protection shall be mounted within the main switchboard to the detailed recommendations of supplier/manufacturer.
Spare spaces for future circuits - specify to a minimum total of:
Where high numbers of spare spaces for future large circuits are involved (eg. 5 controls greater than 160 amps), specify the switchboard and switchroom space to be suitable for addition of future extension cubicle/s. Provide busbars sized for the anticipated additional load.
Provide the following sections on each EDB:
These sections may be arranged in a single compartment or in adjacent compartments. Additional compartments may be required to house time switches, contactors, relays, etc. Separate shrouded compartments are not required.
The incoming control may be a fault-make load-break switch or a circuit breaker with a current rating equal to the supply-end submain protection. Discrimination between the incoming control and the submain protection is not required.
Busbars are required from the mains connection point to the line side of all circuit breakers.
Provide
Refer to DG / ELECTRICAL SERVICES / SPARE CAPACITY
Long cable runs are common in schools and, as required by AS/NZS 3000, cable selection needs to address factors additional to current carrying capacity.
One of the factors that must be considered is voltage drop. Calculate voltage drop using maximum demand determined from the process further outlined. In the case of final subcircuits, consider the circuit carrying a current equal to the rating of the circuit protective device. Refer to Wiring Rules AS3000 for voltage drop permissible where there is a direct connection to a substation.
Note that voltage drop must be considered from the point of supply to the last item on any final subcircuit. The permissible voltage drop is the sum of the individual drops in (a) the service/consumers mains, (b) any submain/s and (c) each final subcircuit. The proportioning of the voltage drop across (a), (b) and (c) will vary from site to site to achieve an economic solution.
As a general rule, limit final subcircuit length to servicing loads not more than 25m radius from the EDB. In a heavily loaded building such Science or Materials Technology, the 25m radius criterion may need reducing. There may, however, be other situations where it is economic to slightly increase final subcircuit cable lengths with a corresponding reduction in the permissible submain/s voltage drop from the originating power source to the EDB (e.g if it avoids duplicating an EDB).
Ensure that the maximum voltage drop allowed by relevant AS will not be exceeded at any point in the installation in the future when the spare capacity is used and future buildings are added. In terms of the future, make due allowance for voltage drop in submains to future buildings, and base the calculation on final subcircuits in future being to the 25m radius criterion.
Cables are to be continuous from the point of supply to the MSB, from the MSB to EDBs and between EDBs. Cables are not to be joined.
Conceal all wiring and conduits wherever possible. The choice of wiring system will be influenced by the construction and finish of each wall, floor, ceiling, etc. and any potential hazard, eg. exposure to weather, mechanical damage.
Acceptable wiring methods are:
Refer to DG / SPECIAL ELECTRICAL SYSTEMS / SKIRTING AND WALL MOUNTED DUCT
Consistent with design requirements and wherever possible, minimise costs arising from cutting and chasing masonry by locating wall mounted outlets on accessible walls (eg. cavity walls).
Single brick walls, face both sides, are a common construction in schools, and require “biscuiting” of bricks or other cutting to allow conduit access. Rendered brick walls or other masonry construction require chasing.
A typical drawing is included in the Specification Guide - Drawings, which relates to orientation of wall-boxes in standard brickwork, and places restrictions on the socket outlet types acceptable.
Inform the Project Architect as early as possible of any need to cut bricks, chase, etc. and provide an indication of the total lengths involved to the Quantity Surveyor.
Embedded conduits displace their own volume in concrete and, depending on their location, number and spacing, could affect the structural performance of a slab or column.
A high concentration of conduits occurs at switchroom and switchboard cupboards.
Exercise caution with embedded conduits in areas where slab penetrations will occur, e.g.:
In the latter case, run conduits around the floor slab, not across it.
All conduit runs in slab and penetrations to structural elements must be approved by the structural engineer prior to installation.
Preliminary maximum demand figures can be calculated using square metre rates as outlined in AS3000.
The preliminary maximum demand may be used to enable negotiations with the electricity distributor to begin early in the design process. However, for more accuracy, use this section in conjunction with requirements of the relevant AS, particularly when detail layouts are available.
Refer to DG / ELECTRICAL SERVICES / PERMANENT SUPPLY TO SITE
For buildings (particularly demountables) being placed on site at the completion of the main project, calculate maximum demand by considering electrical heating figures.
Socket outlets are not intended to be used in schools for the connection of portable electric space heating or cooling appliances. Permanently installed heating is provided, as is cooling equipment where necessitated by the climate conditions. Interpretation of this needs to be agreed to by the relevant authorities for each site.
Calculate the maximum demand of each building to be constructed or refurbished using AS 3000.
For refurbished buildings, the maximum demand calculation must also deduct the electrical loads being removed or being replaced.
Determine the maximum demand of existing buildings that are being connected to the reticulation system by calculation or by installing temporary data loggers within the switchboards to record the demand for a period of minimum 4-weeks.
Design the reticulation to supply all buildings, include those planned for construction in the future and for planned demountable buildings.
Refer AS/NZS3000
Where the site plan shows proposed or existing buildings which are not part of the project under documentation, make provision in the electrical design for these buildings in an appropriate manner as listed below.
a) Existing Buildings Being Retained
Incorporate the submains to these buildings in the overall design. Assess their demand, and if necessary, run new submains, controls, and other cabling. Existing external cabling may be re-used if its condition and rating are satisfactory. If a new MSB is required, rationalisation of the cabling may be preferable.
b) Proposed Extra Buildings
Demountable and other buildings are often placed on site immediately after the completion of the main project, increasing the school's capacity for a few years.
Ascertain the number, locations and type of these additions, then design and install the reticulation to cater for them. Provide submain controls on the appropriate EDB, and run spare conduits to points clear of hard surfaces.
Refer to DG / ELECTRICAL SERVICES / SPARE CONDUITS FOR FUTURE USE
The submains and buildings will be by others. Note that demountables usually have reverse cycle air conditioning.
c) Future Buildings
Buildings identified as “future” may not be installed for some years, but are to be incorporated into the reticulation using the guidelines below. As part of ‘Whole of life’ approach consider the potential future expansion of service requirements and include allowance where feasible.
Provide spare capacity in service/consumer mains, submains and distribution boards as follows:
Do not install the cables for future buildings. Install properly sized conduits with draw cords from the appropriate EDB to a point 1m clear of hard surfaces.
Provide spaces only, not sub-main controls, for future buildings.
Provide a complete set of operating and maintenance instructions at the time of handover of the building/s.
Include information to guide staff in:
Information needs to be developed for the specific installation and application.
Avoid material that is not specific to the installation.
Include all equipment installed or connected as part of the electrical services. This is to include, but is not limited to:
DG61/1 Conduit to Single Skin Brickwork